How Often Should You Take Progress Photos on a Build?
Construction28 November 20264 min read

How Often Should You Take Progress Photos on a Build?

How often should you take progress photos on a construction site? Most builders I fly for in Melbourne settle on monthly drone photos, with extra visits when the job is moving fast or a stage payment is due. That's the short version. The right number depends on how quickly the site changes and who is reading the photos.

Here's how I'd set the schedule for a typical house or mid-size commercial job.

Start with monthly

Monthly works for most builds. A house in Point Cook or a block of townhouses in Reservoir doesn't change enough week to week to justify more aerials. A month gives you a visible difference between frames: a new slab, or a roof that wasn't there last time.

It also lines up with how most people report. Developers and lenders tend to want a monthly update, so the photos land when the report is being written.

Go fortnightly during structure

The exception is the structure stage on bigger jobs. Once the slab is down on a three or four storey apartment build, a level can go up in a week or two. Shoot monthly and you skip whole floors.

I'd switch to fortnightly from the first slab until the roof is on, then drop back to monthly for fit-out. Fit-out happens inside, and a drone can't see much of it from 50 metres up.

Add a visit for each milestone

On top of the regular dates, book a flight for the moments people will ask about later:

  • site cleared, before excavation starts
  • footings or piles in, before the slab pour
  • slab finished
  • frame or structure complete
  • roof on and lock-up
  • landscaping done, at handover

These roughly match the stage payments in most Victorian domestic building contracts (base, frame, lock-up and completion), so a dated aerial at each one gives the owner or the bank something to look at when you lodge the claim.

What changes the schedule

A few things push the number up or down.

How fast the job moves. A slow civil job with long quiet patches can go to every six weeks. A fast commercial build in Richmond with three trades on site might need fortnightly for months.

Who reads the photos. If the client lives interstate or overseas and never visits, they'll want to see more. A local owner who drives past every Saturday probably won't.

Disputes and variations. If a neighbour has complained or there's a variation brewing, extra dated photos are cheap insurance. The original files carry the date and GPS position, which helps if anyone questions when something happened.

Melbourne weather. Wind and rain will cancel some flights, mostly in winter and spring. Agree a fallback rule at the start, such as "the next clear weekday", so the gaps between photos stay roughly even.

Weekly is rarely worth it from the air

Some site managers ask for weekly drone flights. For most jobs I'd say no. The frames look almost the same and nobody scrolls through 52 of them.

Daily and weekly records are better done on the ground by the site team. A phone photo of the pipework before the plasterboard goes on is worth more than any aerial. Use both: phones for the detail, the drone for the overview once a month.

Keep the frames the same

The schedule only helps if each set can be compared with the last. That means the same positions and heights on every visit, shot at about the same time of day. I wrote up how I do that in how to shoot construction progress photos that line up.

Name the files by date so they sort in order, and keep the full-size originals even if you only send small copies around.

Setting it up

Book the whole job as a recurring visit, not one shoot at a time. Pick a day of the month, add the milestone flights as the program firms up, and let the pilot know when a pour or a crane lift is coming.

If you'd like help working out a schedule for your site, have a look at our construction progress photography service or send the address and build program through the quote page. I'll suggest a cadence that suits the job.